Posted on: June 21, 2018

Dairy Road M-1 Culvert Replacement Construction Progress Update

Earlier this Spring, construction was delayed somewhat due to rains causing some material to enter into certain formed up areas for headwall footers. This material had to be removed prior to the concrete pours for the footers. Construction of the headwall and wingwall footers, and headwalls and wingwalls themselves are now complete.

The replacement culvert, in place for some time now, is much longer than the failed culvert it replaced. This will make for an easier future year roadway widening from two to four lanes.

The current projection for substantial completion is mid-July.