West Melbourne is committed to an active water looping and water line replacement program.

The following sewer system improvements are scheduled for construction in 2022-2023:

  • Sewer Treatment Plant Improvements (Spring 2023)
  • Meadowlane Avenue force main replacement (Spring 2022)
  • Hollywood Boulevard Reuse Main replacement (Winter 2022)
  • Lift station rehabilitations of the Phantom Fireworks lift stations (Spring 2022)

 

The following water system improvements are scheduled for construction in 2022-2023:

  • Installation of a new water main along the M-1 Canal from Dairy to Wickham (Spring 2022)
  • Installation of a new water main along Fell Road west of Minton (Spring 2022)
  • Replacement of water mains in the Melbourne Estates/Henry Avenue area (2023)
  • Construction of a new Water Treatment Plant (2024)
  • Construction of three new raw water wells (2024)
  • Water main crossing at 192 (2023)
  • Water main crossing Wickham Road (2023)
  • Dundee Circle and Manor Place Loop (summer 2022)

  

The following stormwater improvements are scheduled for construction in 2022-2023:

  • Melbourne Estates drainage improvements (2023)
  • Construction of new stormwater retention pond on underutilized Wastewater Treatment Plant property (Spring 2022)
  • Southwest Shannon Avenue Head Wall (Summer 2022)