West Melbourne is committed to an active water looping and water line replacement program.
The following sewer system improvements are scheduled for construction in 2022-2023:
- Sewer Treatment Plant Improvements (Spring 2023)
- Meadowlane Avenue force main replacement (Spring 2022)
- Hollywood Boulevard Reuse Main replacement (Winter 2022)
- Lift station rehabilitations of the Phantom Fireworks lift stations (Spring 2022)
The following water system improvements are scheduled for construction in 2022-2023:
- Installation of a new water main along the M-1 Canal from Dairy to Wickham (Spring 2022)
- Installation of a new water main along Fell Road west of Minton (Spring 2022)
- Replacement of water mains in the Melbourne Estates/Henry Avenue area (2023)
- Construction of a new Water Treatment Plant (2024)
- Construction of three new raw water wells (2024)
- Water main crossing at 192 (2023)
- Water main crossing Wickham Road (2023)
- Dundee Circle and Manor Place Loop (summer 2022)
The following stormwater improvements are scheduled for construction in 2022-2023:
- Melbourne Estates drainage improvements (2023)
- Construction of new stormwater retention pond on underutilized Wastewater Treatment Plant property (Spring 2022)
- Southwest Shannon Avenue Head Wall (Summer 2022)